Welcome to the Future of Public Safety in Flathead County
Location
Kalispell, MT 59901
225 Snowline Lane
Kalispell, MT 59901
Contact Info
+1 (406) 758-5501
Flathead County is committed to transparency and open communication throughout the construction process.
We encourage community member to reach out with any questions or concerns. Our goal is to ensure you have the information you need to make an informed decision and understand the full impact of this important project.
In November 2025, Flathead County voters approved a $105 million bond to construct a new Public Safety Facility to house the county jail and Sheriff's Department.
With public approval, the County began the next phase of a long-planned effort to address detention capacity, officer safety, and long-term infrastructure needs.
The current jail was built in 1987 for 63 inmates. Over the decades, Flathead County has grown significantly, while the facility has been stretched beyond its original design. Although temporary expansions increased bed counts, the building’s layout, aging infrastructure, and safety limitations cannot meet modern jail standards or long-term demand.
Where We Are Now
With voter approval secured, the County is actively:
- Finalizing architectural and design details
- Conducting value engineering to ensure thoughtful design decisions that balance functionality, durability, and budget
- Preparing for bond issuance and construction planning
- Establishing oversight and accountability measures
Construction timelines, financial updates, and key project milestones will be shared here as they develop.
Our Commitment
Flathead County has been saving for this project since 2017 and reduced projected construction costs through disciplined planning and value engineering.
The goal remains clear: deliver a facility that is functional, durable, and fiscally responsible—built to serve the public safety needs of Flathead County for generations to come.
This website will serve as the central source for accurate information, project documents, and progress updates.
We appreciate the trust placed in us by the voters of Flathead County and are committed to carrying this project forward with transparency and care.
Timeline
-
Completed: 2017
Project Funding Began
County began setting aside funds for the project.
-
Completed: 2024
Site Purchased & Architect Hired
Purchased 115-acre site at 225 Snowline Lane for $3.9M.
Elevatus Architecture hired (Nov 2024). -
Completed: March 2025
Preconstruction Firm Hired
Martel hired for preconstruction.
-
Completed: Aug 7, 2025
Bond Placed on the Ballot
Commissioners passed a resolution to place a $105M bond on the November 4, 2025 ballot.
-
Completed: Nov 4, 2025
Bond Election Passed
-
Completed: Feb 2026
Bond Issuance Resolution Approved
The Board approved the bond issuance resolution — the official legal step that lets the county begin selling bonds.
Approved Feb 12, 2026; the actual bond sales are expected April 14, 2026, timed to have cash on hand for groundbreaking. -
Completed: March 2026
Owner's Representative Appointed
The Board officially appointed In2itive Architecture as the Owner's Representative
-
Completed: March 24, 2026
AA+ Credit Rating Earned
Flathead County earns an AA+ credit rating from S&P Global Ratings for the voter-approved Public Safety Facility bond
-
Completed: April 14, 2026
Bonds Sell — Project Fully Funded
95 million in bonds sell, fully funding the project.
-
Completed: April 28, 2026
RFQ for Geotechnical Engineer
Published notice of RFQ for a Geotechnical Engineer.
-
May 7, 2026
Early Ground-Stabilizing Contract Signed
Signed a contract with Martel to begin early ground-stabilizing work.
-
Completed: May 22, 2026
Inspection & Testing Contract Awarded
Awarded a contract to Alpine Geotechnical for special inspections and testing.
-
Completed: June 11, 2026
Guaranteed Maximum Price Finalized
Finalized a Guaranteed Maximum Price contract with Martel Construction — nearly 4% under initial budget projections.
-
Completed: June 2026
Groundbreaking
-
Current step: July 13, 2026
Site Preparation
Begin site preparations
-
Upcoming:
Engineered Aggregate Piers
-
Upcoming:
Utility Infrastructure
-
Upcoming:
Foundations
-
Upcoming:
Building Enclosure / Precast Concrete Panels
-
Upcoming:
Prefabricated Steel Cells
-
Upcoming:
Mechanical, Electrical, and Plumbing
-
Upcoming:
Interior & Exterior Finishes
-
Upcoming:
Furniture & Equipment Installation
-
Upcoming:
Inspections & Testing
-
Upcoming:
Owner Training
-
Upcoming:
Occupancy Transition
-
Upcoming: 2029
Grand Opening